Friday, August 14, 2009

Update 8.14.09

*Granite countertops were installed in the kitchen and all of the bathrooms
*Kitchen sink and all bathroom sinks were installed
*All faucets were installed
*Toe moulding has been installed
*Screening has been installed on the back porch (minus the door for now)
*Security system has been installed
*Patio has been scored
*Treads on the stairs have been stained to match the hardwood floors

A great deal of work had been done yesterday! The end is near! YAY!